MDT addresses concerns about Ronan highway project
Hey savvy news reader! Thanks for choosing local.
You are now reading
1 of 3 free articles.
News from Sloane Stinson, MDT
RONAN — Riverside Contracting, Inc. will continue miscellaneous site cleanup throughout the project area the week of July 10.
Streetlight installation will also resume along US Highway 93. Single-lane closures may be required where work is occurring. The speed limit remains at 35 mph in the construction zone.
On Round Butte Road, crews will be installing road signs. Crews will be onsite Monday, July 8, through Friday, July 12, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Work on a solution to address the community’s concerns regarding the newly realigned intersection of US 93 with Old US 93 and Third Ave. continues. MDT is committed to improving the intersection. We appreciate your patience and will provide an update as soon as possible.