Ronan road construction to pause for Memorial Day
Hey savvy news reader! Thanks for choosing local.
You are now reading
1 of 3 free articles.
News from Sloane Stinson, MDT
RONAN — The Montana Department of Transportation (MDT) and Riverside Contracting Inc. have the following work planned for May 20 to May 23. All work is dependent on weather and other unforeseen factors.
On Round Butte Road, sidewalk work continues east of the railroad tracks. Flaggers will periodically help facilitate safe travel where work is underway.
Installation of the traffic signal poles and streetlights along US Highway 93 (US 93) also continues. Single-lane closures may be required where work is occurring.
Other planned site work includes installing pedestrian handrails and gates throughout the project area.
Crews will be onsite tomorrow, Saturday, May 18, and Monday, May 20, through Thursday, May 23, from 7 a.m. to 6:30 p.m.
Work will pause for the Memorial Day holiday weekend starting on Friday, May 24, through Monday, May 27 to accommodate increased holiday traffic and to give workers time to spend with their families. Crews will return on Tuesday, May 28.