Highway 93 construction operations continue in Ronan
Hey savvy news reader! Thanks for choosing local.
You are now reading
1 of 3 free articles.
News from Big Sky Public Relations on behalf of the Montana Department of Transportation
RONAN — Excavation operations continue this week at the project’s north end, north of Baptiste Road. Traffic will be traveling on the southbound lanes, and drivers should anticipate traveling on a gravel surface through this section of the project area.
Installation of underground electrical conduit to support the new streetlights and the Old US 93 and 3rd Avenue intersection traffic signal also continues.
On Round Butte Road, sidewalk and curb construction has been suspended until early fall.
Next week, crews will be onsite Monday through Friday from 7 a.m. to 6:30 p.m.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
Please do not hesitate to reach out with any questions or concerns. Email me directly at sloane@bigskypublicrelations.com or call the project hotline at 406-207-4484, Monday through Friday, 9 a.m. to 5 p.m. For more information on the Ronan-North project, visit bit.ly/Ronan-North.